Fort Worth Museum of American Art:
Fort Worth Texas
Linbeck Construction
Superintendent
December 1999 - August 2003
Project Amount: 60MM
Project SF: 50,000
Type of Project: Architectural Concrete
Responsibility:
• Planned and supervised the basement excavation in the blue shell. Dewatered and removed muck from the site.
• Excavated rock for basement underfloor plumbing and electrical lines.
• Planned and supervised spread footing installation. Formed and poured structural walls and basement slab on grade.
• I had step designed for sloped areas to support slab on deck shoring.
• Planned and poured 600 LF 3‘high x 6‘wide step footing for site architectural concrete walls.
• Conducted weekly site safety meetings.
• Used AutoCAD to draw ‘Y’ column shop drawings and demonstrate erection and pour sequence.
Special Recognitions:
• 2002 American Subcontractor Assoc. Outstanding Project
• 2002 TX Building Branch Outstanding Construction
• 2003 Build American Award
• 2003 CRSI Design Award
• 2004 Dallas Business Press Top Ten Award